Traffic, Roads, & Bridges

National Structures Inc. has been contracted by the County of Lennox & Addington to rehabilitate the Morven Bridge located on County Road 2 in Morven. The work generally consists of replacement of concrete curbs and railings, bridge deck repairs and re-paving.

To facilitate the work the bridge will temporarily be restricted to a single lane for traffic controlled by portable traffic signals. Traffic delays should be expected.  Cyclists and Pedestrians will be able to cross the bridge while this work is ongoing.

The work is scheduled to start on approximately June 7, 2021 and is scheduled to be completed by approximately October 28, 2021.

We apologize for any inconvenience this may cause and appreciate your patience.

Should you have any questions or require further information please contact:

Dan Baxter
Engineering Technologist
613-354-4883 Ext 3228