The Town of Greater Napanee and the County of Lennox and Addington has started a reconstruction of Dundas Street between Hessford Street and Adelphi Street. The three-year project will update infrastructure and will beautify our historic street.

 

BannerAd-WEBSITE.jpg

 

News & Updates

Effective June 2nd

Diggin Downtown - Dundas Reconstruction Phase 1 Closure 3.jpg

Len Corcoran Excavating Ltd. (LCE) crews are currently working on completing the underground services on Diggin' Downtown Napanee within the Centre Street to Robert Street block. Dundas Street is currently closed from Centre Street to West Street.

Construction crews have completed the replacement of sewer and watermain infrastructure within the 1st block of construction from Robert Street to the east side of the Centre Street intersection and will soon begin replacement from West Street to Robert Street. Installation of new traffic signals has begun at the intersection of Dundas Street & Centre Street.

It is anticipated that the reinstatement of concrete curbs and gutters will begin within the next week between Robert Street and Centre Street with asphalt paving occurring shortly after.

Due to weather and unforeseen delays to the construction schedule, it is estimated that Dundas Street from Robert Street to Centre Street will remain closed to traffic until Friday, July 14th.

Note that LOCAL TRAFFIC (not thru traffic) can by-pass the barricades to enter all LOCAL TRAFFIC / NO EXIT blocks in the area.  Access to the 2 blocks under construction will be provided to Emergency Service Providers and pedestrians. Residents and Businesses within the 2 blocks under construction will be kept advised of access availability.

Ongoing notices will be given to advise of future block closures as work progresses.  

We appreciate your patience during the construction.  Should you have any questions or require any further information please contact one of the following or speak with any senior staff on site wearing a white hard hat or contact Diggin' Downtown Napanee's Community Liaison Officer.

 

Find up-to-date information on scheduled road closures, resident notices, newsletters, and media releases.

Check out our Diggin' Downtown Facebook page for unanticipated and short notice announcements. On Twitter, #DiggingDowntown will be incorporated into all tweets related to the project from Lennox & Addington’s account (@LandACounty).

 

Project Details

Diggin Downtown - Dundas Reconstruction Phase Map

The first phase of the project is anticipated to begin in April. The timetable for construction is as follows:

Phase 1 (Centre Street west to Robinson Street)

  • February 2, 2017 – Public Information Centre
  • February 2017 – Tendering
  • March 2017 – Award of Tender
  • April 2017 – Commence Construction
  • October 2017 – Complete Construction

 

Phase 2 (Centre Street east to Adelphi Street):

  • November 2017 – Public Information Centre
  • January 2018 – Tendering
  • March 2018 – Award of Tender
  • April 2018 – Commence Construction
  • October 2018 – Complete Construction

 

Phase 3 (Hessford Street east to Robinson Street):

  • November 2018 – Public Information Centre
  • January 2019 – Tendering
  • March 2019 – Award of Tender
  • April 2019 – Commence Construction
  • October 2019 – Complete Construction

 

Business Support

Lennox & Addington County will be offering support to businesses in the downtown during the reconstruction project.

 

Communications

Communications will be key to a successful project. Our goal is to ensure that all BIA members feel connected and involved during construction. The County of Lennox and Addington will be leading construction communications. BIA Members and the public will be kept up to date through a website portal, social media, e-blasts and newsletters. Joe Hogan, our Construction Liaison Officer will be your connection to the project. This individual will be onsite and will ensure that communications are timely and clear. He will be available to listen to concerns and will be your link to the contractor and the municipality. Joe can be contacted at 613-539-7657 or via email by clicking here

 

Tech Coaching

The County of Lennox and Addington has resources available to help you build your online presence. Our Tech Coach can help you create an e-commerce solution to open up new markets, attract new customers and produce new revenue. This can help to maintain and grow current sales revenue during construction. Learn more about our Tech Coaching services.

 

Business Coaching

The Lennox and Addington Economic Development Office offers free business coaching. Tracey Snow is available to work with BIA Members to develop a plan for the upcoming construction. This could include inventory management, staffing strategies and marketing. Give Tracey a call at 613-561-6310 to book an appointment. Please click here for more details about our business coaching services. 

Construction Tips For Your Business