The County is responsible for administering all construction activities on County roads. This may include engaging an engineering consultant to provide design, contract administration and construction inspection of theses projects on its behalf. A draft design is presented to Technical Advisory Committee-Roads and Bridges (TAC) for preliminary approval before the project is tendered. County staff works closely with the consultant and local road authorities in developing the project’s design and overseeing its administration throughout the design, tender and construction phases and payment approval.
County Technical Advisory Committee - Roads & Bridges
The County’s annual capital construction program is developed in consultation with the County Technical Advisory Committee-Roads and Bridges (TAC). TAC’s membership is comprised of County staff (Manager, Roads & Bridges, Operations & Development and Construction Technologists, and Director, Financial & Physical Services) and the road authority managers from each local municipality. The TAC committee also serves as a forum to review County road operational issues and matters of interest to both the County and local municipalities. TAC meets 6 times per year and meeting minutes are provided to County Council in its regular monthly meeting agenda.
- County Road 11
- 5.0km
- 3.7km west of County Road 41 to County Road 10 (Greater Napanee)
- Interim road stabilization and drainage improvements
- $150,000
- County Road 41
- 1.3km
- Green/White Lake Road to County Road 13 (Stone Mills)
- Road rehabilitation, drainage and safety improvements (BCF-1*), continuation of 2009 project *Building Canada Fund Communities Component - Intake 1
- $637,000
- County Road 41
- 10.0km
- Hwy. 7 at Kaladar to 10.0 km southerly (Stone Mills/Addington Highlands)
- Road rehabilitation, drainage and safety improvements (ISF**), continuation of 2009 project **Infrastructure Stimulus Fund
- $6,330,000
- County Road 9
- 5.4km
- 1.6 km wast of Fitchett Road (River Rd) to 1.0 km west of Abrams Road (Greater Napanee)
- Surface treatment program (including rehabilitation, padding and edge repairs)
- $316,778
- County Road 9
- 1.8km
- 0.8 km east of Fitchett Road to 1.2 km west of Cuthill Lane (North Shore) (Greater Napanee)
- Surface treatment program (including rehabilitation, padding and edge repairs)
- $96,847
- County Road 9
- 1.2km
- 1.2 km west of Cuthill Lane to Cuthill Lane (Greater Napanee)
- Surface treatment program (including rehabilitation, padding and edge repairs)
- $71,862
- County Road 30
- 4.5
- Hwy. 41 to Tower Matawatchan Road
- Surface treatment program (including rehabilitation, padding and edge repairs)
- $212,560
- County Road 1 (Belleville Road)
- CNR Overpass
- 0.5 km west of Marilyn Street (Greater Napanee)
- Miscellaneous concrete guide rail, expansion joint and handrail repairs/replacements
- $740,000
- County Road 41
- Centre Street CNR Underpass
- 0.2 km south of Advance Avenue (Greater Napanee)
- Concrete sidewalk and retaining wall repairs
- $242,000
- County Road 5
- 0.7km
- County Road 5/18 curve and to 650m easterly (Greater Napanee)
- Intersection curve edge repairs, pavement rehavilitation and 1.2m wide paved shoulders
- $211,000
- County Road 6
- n/a
- County Road 2 to Hwy. 401 in Odessa (Loyalist Township)
- Paved shoulders/Hwy. 401 overpass drainage improvements
- $166,000
- County Road 8
- 3.3km
- 0.5 km south of Galt Street to County Road 21 (Greater Napanee)
- Rehabilitation, 1.5m wide paved shoulders
- $1,154,000
- County Road 29
- n/a
- Flinton Road from Hwy. 41 to 4.4 km westerly (east limit of Flinton (Addington Highlands)
- 1.2m to 1.5m wide paved shoulders/stabilization
- $419,000
- County Road 41
- 0.6km
- Centre Street from Dundas Street to Isabella Street (Greater Napanee)
- Surface rehabilitaiton, includes 2 Bell MH rehabilitations
- $322,000
|